NER Power System Improvement Project(NERPSIP)

Project Information:

  • 1. Sanctioned cost of the project - Rs. 1372.20 Cr.

    2. Revised sanctioned cost of the project – Rs. 1800.28 Cr.

    3. Funding pattern - 50 : 50 between Govt. of India and World Bank.

    4. Implementing Agency : Powergrid Corporation of India Limited.

    5. All works awarded.

Project Outcome:

The project shall provide a robust power network in the State and improve reliability, which consists of transmission and distribution components. The project also aims to improve the intra-state transmission and sub-transmission infrastructure to facilitate an increased availability of power to the consumers, improve service delivery, and reduce system losses.

Physical Progress:

SL.No

Component

Scope

Progress(%)

Completion Target

1

New 132 KV Sub-station.

9 nos

80%

Anitcipated completion: In phases by Dec, 2021.

2

Augmentation /Extension of existing 132 KV Sub-staion.

7 nos

80%

3

New 132 KV Transmission line

458 CKM

70%

4

New 33 KV Sub-station

34 nos

57%

5

Augmentation /Extension of existing 33 KV Sub-station.

25 nos

48%

6

New 33 KV line

617 KM

40%

7

Reconductoring of 33 KV line

326 KM

0%

8

Optical Ground Wire Installation for Communication

532.35 KM

50%