NER SYSTEM STRENGTHENING SCHEME (NERSS) : TRIPURA(Rs. in Cr.):

SL.No

Name of the Project

Package Cost(Rs. in Cr)

Remarks

Present Status

1

2

3

4

5

1

40 KV Sub-station (ISTS) at Surjamaninagar, West Tripura.

TCB Mode

Implementing Agency:-NER-II Transmission Limited, New Delhi.

All Completed

2

400 KV Sub-station at Purba Kanchanbari, Unokoti District, Tripura.

3

400 KV Double Circuit Transmission Line from Surjamaninagar Sub-station to Purba Kanchanbari Sub-station.

4

132 KV Double Circuit Transmission Line from AGTPP(NEEPCO) to Purba Kanchanbari (TSECL) along with 2(two) nos. 132 KV bays each at AGTPP(NEEPCO) and Purba Kanchanbari(TSECL).